The Workshop 2

 

Quick Links
Page 1

Page 2

Page 3

BACKFILLING

Trench is filled with 6″ sand, caution tape, and filled with dirt. By hand.

DSC04035

DSC04039

Foundation is backfilled. Next is leveling, then the slab.

DSC04367

DSC04366


So I started putting some walls up.

walls001

I spent the day leveling and compacting and leveling and compacting.

DSC04420

At any rate, with any luck, slab poured next week.



Extruded C-300 foam for under the slab, cut outs make 6″ concrete under future hoist:

foam01

foam02


More walls, waiting on concrete:

DSC04455

DSC04456


We got slab! I neglected to ensure that the ground was level enough, so I ended up with a 6″ pour – that’s 8″ under the hoist posts!

image


FRAMING

Trusses arrived, so the overhead-door lintel was put in place. This actually took a lot longer than expected, so no roof trusses got done.

DSC04489


Got the trusses up above the machine shop area. Last doubled truss is a girder truss, which supports the end of the scissor trusses.

DSC04490


Trusses are up. Gotta finish the overhang and sheath the roof. Trusses were probably the least fun.

DSC04513


ROOFING

Still trying to beat Old Man Winter and get shingles on ASAP. Got a fair bit done on the back side, hope to finish sheathing the front tomorrow. Hoping….

image (2)

image


Today I finished sheathing the entire roof, and got half the front slope shingled.

DSC04526

The shingles took 20 hours by my lonesome. VERY exciting to be inside, dry, while a torrential downpour put my handiwork to the test.


DOORS

For the framing inspection, I need to show rough-in of doors, windows, gas, and electrical. So I called up the gas guy.

But the gas guy wouldn’t do any gas work without any doors.

And the door guy wouldn’t install without drywall.

And the drywall can’t be done if it isn’t enclosed and warm.

And I can’t do drywall until I pass the framing inspection.

It’s as if these people don’t work together or something.

The inspector gave me the go-ahead to install doors, so that is what I am finalizing at the moment. Also spoke with the Electrical guy to figure out what we need for a plan and materials.

Brought home the Man Door today.

image


18×9′ Roll up door installed! Anchor Door in Kelowna did a great job!! They also did a matching (but smaller) door on the house garage.

IMG_20151208_081131885_HDR

With this, my self-imposed goal of getting to lockup by the fall, was realized.


HEATER

Workshop heater installed. All wire pulled. Also three network drops and a phone line. Gotta pull coax for cable still, and BX for the heater.

DSC04587
Heater and breaker panel

DSC04588
Further along that wall, moving to the left

DSC04589
The 12×20′ machine shop area

DSC04590
Heading back into the vehicular area

DSC04591
Back at the man door